AMR each-picking — Q1 rollout
- Customer
- Anonymized 3PL
- Vendor / robot
- Vendor A — 12 × AMR
- Workflow
- Each-picking
- Site
- 220,000 sq ft 3PL fulfilment centre24/6 shifts · WMS-integrated (Manhattan Active WM)
- Pilot period
- 12 weeks measuredAmbient 28–34°C · avg 31.0°C
- Evidence tier
- Tier 3Self-reported
01Verdict
Proceed to a phased rollout, conditional on the vendor closing the gaps on availability and interventions. Re-measure all acceptance gates at 90 days.
- AvailabilityRequired ≥ 92%Measured 91.2%
- InterventionsRequired ≤ 10 / 1,000 tasksMeasured 14.3 / 1,000 tasks
- Claim
- 99%
- Gate
- ≥ 92%
- Claim
- 480 h
- Gate
- ≥ 200 h
- Claim
- n/a
- Gate
- ≤ 60 min
- Claim
- 99%+
- Gate
- ≥ 95%
- Claim
- “minimal”
- Gate
- ≤ 10 / 1,000 tasks
- Claim
- £0.11
- Gate
- ≤ £0.15
- Claim
- 18 months
- Gate
- ≤ 24 months
02Vendor claims vs. demonstrated performance
| Metric | Vendor claim | Demonstrated (12 wk) | vs. claim | Gate | Result |
|---|---|---|---|---|---|
| Availability | 99% | 91.2% | 7.8 pts below claim | ≥ 92% | Miss |
| MTBF | 480 hcalculated, 25°C | 212 h@ 31°C avg | 56% below claim | ≥ 200 h | Below claim |
| MTTR | n/a | 47 min | No claim made | ≤ 60 min | Pass |
| Mission success | 99%+ | 96.8% | 2.2 pts below claim | ≥ 95% | Below claim |
| Interventions | “minimal” | 14.3 / 1,000 tasks | Unquantified claim | ≤ 10 / 1,000 tasks | Miss |
| Cost per pick | £0.11 | £0.14 | 27% worse than claim | ≤ £0.15 | Below claim |
| Payback | 18 months | 22 months | 22% worse than claim | ≤ 24 months | Below claim |
Result is measured against the buyer’s acceptance gate. “vs. claim” compares the demonstrated figure with the vendor’s own claim, under the vendor’s stated definition where one was given.
03What the claims hid
- F1The 99% availability figure assumed 25°C ambient and excluded charging time and scheduled safety checks. Measured with nothing excluded, demonstrated availability was 91.2% — 7.8 points lower; charging consumed 6.3% and safety checks consumed 0.1% of required operating time.
- F2The 480 h MTBF was a calculated prediction at 25°C; the fleet demonstrated 212 h at a 31°C average — 56% lower.
- F3At the customer's 31°C average, thermal faults were the #1 failure cause (38% of 98 failure events).
- F461% of interventions were exception handling (damaged / unreadable items) — work that shifted to humans rather than disappearing. At ~2 minutes per intervention, that's ~305 hours of operator time over 12 weeks — roughly 68% of a full-time role shifted onto your floor team. The vendor described interventions as “minimal” without a figure; the pilot measured 14.3 per 1,000 tasks.
04Safety & compliance
ISO 3691-4 safety functions verified at commissioning; periodic checks confirmed quarterly.
Vendor verification method: combination (ISO 3691-4, CE, UKCA). Stated check frequency post-commissioning: quarterly. Measured safety-check downtime averaged 35 min/robot/month of availability. 3 safety events / near-misses recorded over 12 weeks.
05Risks & conditions
- aVendor to demonstrate availability ≥ 92% (measured 91.2%) at re-measurement.
- bVendor to demonstrate interventions ≤ 10 / 1,000 tasks (measured 14.3 / 1,000 tasks) at re-measurement.
06Recommendation
Proceed to a phased rollout, conditional on the vendor closing the gaps on availability and interventions. Re-measure all acceptance gates at 90 days.
07Evidence appendix
Includes generated demo pilot data. These results are illustrative, not verified deployment evidence.
- REPORT REF
- RV-SAMPLE
- WEEKLY RECORDS
- 12
- INPUT HASH
- 1d046618dd318c86
- GENERATED
- 17 Nov 2026
- Tier 1Verified
- Tier 2Attested
- Tier 3Self-reported
Vendor-submitted, unverified.
Weekly pilot record
| Week | Temp | Op. hours | Completed | Failures | Avail. | MTBF h | MTTR min | Success | Int./1k | £/pick |
|---|---|---|---|---|---|---|---|---|---|---|
| W1 8 Jun | 28.4°C | 1,728 | 46,565 | 5 | 92.4% | 346 | 43 | 95.2% | 16.4 | £0.160 |
| W2 15 Jun | 29.2°C | 1,728 | 50,355 | 7 | 92.2% | 247 | 46 | 95.8% | 15.7 | £0.150 |
| W3 22 Jun | 30.0°C | 1,728 | 53,063 | 8 | 91.7% | 216 | 36 | 96.3% | 15.2 | £0.143 |
| W4 29 Jun | 30.9°C | 1,728 | 54,146 | 9 | 91.1% | 192 | 47 | 96.6% | 14.9 | £0.140 |
| W5 6 Jul | 31.8°C | 1,728 | 54,145 | 10 | 90.5% | 173 | 52 | 96.8% | 14.6 | £0.139 |
| W6 13 Jul | 32.6°C | 1,728 | 53,604 | 11 | 90.0% | 157 | 52 | 96.8% | 14.4 | £0.140 |
| W7 20 Jul | 33.3°C | 1,728 | 53,063 | 11 | 89.8% | 157 | 39 | 96.7% | 14.2 | £0.140 |
| W8 27 Jul | 33.0°C | 1,728 | 53,604 | 11 | 89.9% | 157 | 56 | 96.9% | 13.9 | £0.139 |
| W9 3 Aug | 32.1°C | 1,728 | 54,687 | 8 | 91.0% | 216 | 40 | 97.2% | 13.6 | £0.136 |
| W10 10 Aug | 31.2°C | 1,728 | 55,228 | 7 | 91.5% | 247 | 39 | 97.4% | 13.3 | £0.134 |
| W11 17 Aug | 30.1°C | 1,728 | 55,770 | 6 | 92.2% | 288 | 57 | 97.5% | 13.0 | £0.132 |
| W12 24 Aug | 29.4°C | 1,728 | 55,770 | 5 | 92.2% | 346 | 58 | 97.6% | 12.8 | £0.132 |
| Total | 31.0°C | 20,736 | 640,000 | 98 | 91.2% | 212 | 47 | 96.8% | 14.3 | £0.140 |
Failure log by cause
| Cause | Count | Share |
|---|---|---|
| Thermal faults | 37 | 38% |
| Software | 18 | 18% |
| Connectivity | 14 | 14% |
| Charging | 11 | 11% |
| Mechanical | 10 | 10% |
| Operator override | 8 | 8% |
| Total | 98 |
Interventions by cause
| Cause | Count | Share |
|---|---|---|
| Exception handling (damaged / unreadable items) | 5,583 | 61% |
| Rescue (stuck / lost robot) | 2,105 | 23% |
| Restock support | 1,464 | 16% |
| Total | 9,152 |
Methodology notes
- Availability
- uptime ÷ required operating time, where uptime = operating hours − downtime − charging time lost − safety-check downtime. Exclusions: none. Charging and scheduled safety checks count against availability because the robot cannot work during them.
- MTBF
- operating hours ÷ number of failures. Operating hours are fleet robot-hours of required operation. With no failures, MTBF is reported as at least the failure-free operating hours, and passes its gate once those hours reach it.
- MTTR
- total repair minutes ÷ number of failures. With no failures there is nothing to repair, and the MTTR gate passes.
- Mission success
- completed tasks ÷ assigned tasks.
- Intervention rate
- interventions ÷ (completed tasks ÷ 1,000).
- Cost per task
- (robot cost + integration amortization + maintenance + support labour cost) ÷ completed tasks, over the measured period. Support labour cost = support labour hours × fully loaded labour rate. Each week carries 7 days of cost, except a first or last week the pilot only partly covered.
- Payback
- total investment ÷ monthly measured benefit, where benefit = baseline labour cost for the same completed tasks − current total monthly cost. Baseline labour cost = completed tasks ÷ manual throughput per labour hour × labour rate.
- Verdict rule
- GO when every acceptance gate passes; CONDITIONAL GO when at least two-thirds pass; NO-GO otherwise. Gates are compared at the precision shown.
Figures computed by Rovidence from the evidence tier shown. This report is built from generated demonstration data and is not verified deployment evidence.